I'm trying to determine some of the markers that indicate a project of limited resources.
In my experience a project becomes a ‘limited resources’ project because someone was desperate to sell a solution to a client. The results is a tight budget, features are culled and SDLC processes are cut to a minimum. These short-cuts are taken so the company has some chance of making a profit or even breaking even.
This is a list of things which I have seen go hand-in-hand with a project of limited resources:
What other sure signs are there for a limited resources project?
===
EDIT
i will try clear up some of the confusion with an example. this is what i mean: the client is given a proposal/quote saying their project will cost $20k. the client then comes back and says "sorry, my budget is $16k maximum". the boss says "make the proposal $16k - we want this work".
so, effectively, you have to do a project with less budget then it should have. there are boundaries where it becomes ridiculous - if the client was to say "my budget is $4k" then you couldnt possibly do it.
and yes, sometimes a tight budget can become so silly that it was a bad business decision to accept the project in the first place (i.e. doomed project).
i understand that there is no such thing as a project with unlimited budget. often business people make the decision whether a project should be undertaken (a business person often isnt a project manager).
Upvotes: 1
Views: 595
Reputation: 1639
using the information you guys so kindly contributed i was able to pull it all together and write an article
ill put a link here in case someone in the future is looking for help on the topic:
Surviving An Under-resourced Project
--LM
Upvotes: 0
Reputation: 15414
What you are talking about is not a 'limited resources' project, but instead a rushed and unplanned project.
A few items in your list I take issue with:
Actually, these should be the norm for most projects. Who's requesting and paying for the changes, you or the client?
If that's not part of the contract, why are you doing it?
At some point, you have to stop at 'good enough', or else you are going to be polishing from now until the end of time.
Something I would add to your list are:
Upvotes: 5
Reputation: 261
"Under-priced projects"
If I understand correctly what you mean, you really are talking about projects where the resources available to the project are not appropriate to achieve the results that were promised to the client.
I can think of four ways for this situation to arise:
When people in the project become aware of the situation, they really have two options: cut costs or cut scope. Cutting the scope can be a hard sell and may endanger the project viability, so most of the time people opt for cutting custs, especially since cost can be cut in many ways without atracting the attention from the higher echelons:
and so forth.
In fact, you may even look good as a project manager when you start cutting costs, since cost containment is one of the project manager's responsibilities! I assume that what you want is to find ways to diagnose an under-funded project. I think that instead of developing an extensive list of symptoms, I would strive to identify a general condition.
In my opinion, there is a general condition that allows to pinpoint an under-funded project. For most projects, staff is the biggest cost - or at least the second biggest cost that can be managed by the project manager. Whenever you find an experienced manager taking measures to reduce staff costs and those measures were not part of the original plan, then you can be sure you have an under-funded project.
Regards,
Upvotes: 1
Reputation: 14327
Upvotes: 1
Reputation: 2319
Outdated or obviously beta documentation which doesn't jive with whatever release of the product on site, or documentation which looks like it's been down through several generations of Xerox copies.
No onsite installation or support. Depending on the size of the system being implemented, a company in good shape might send one or more of their developers to oversee the implementation, whereas a company that's tight might offer phone or email support only in a more "fire and forget" approach.
Upvotes: 1
Reputation: 88092
Quite frankly, I've never heard of a project that had unlimited resources. Even the government will put the brakes on something after a while.
So, from a pure logic perspective, all projects have limited resources.
Upvotes: 2
Reputation: 68328
Limited resources? All projects that I know of have limited resources: