In TFS2012, how do you change what's displayed in the task board?

When I navigate to the Task Board in TFS2012 Web Access, there is a message stating the following:

The task board cannot be displayed because it is empty. You have configured the task board to show work scheduled for the following iteration: BP5578-CouponMaint\Sprint 001.

I have no idea how this was configured (or whether it's really just a default). How do I configure which iteration shows on the Task Board?

Upvotes: 2

Views: 1924

Answers (2)

DaveShaw
DaveShaw

Reputation: 52818

The sprint shown will be current one. This is based on going into the Settings "cog" and then Iterations, and finding the ones that are ticked and has today's date in it's date range, in your case it will be: BP5578-CouponMaint\Sprint 001. Along side it, there should be other sprints and the dates that these sprints cover.

Upvotes: 0

Dylan Smith
Dylan Smith

Reputation: 22255

The taskboard will show the current iteration, which is based on the iteration dates you configured.