My team is using TFS 2010 Agile template, and I wanted to enforce developers to fill out Completed & Remaining hours upon check-in.
Any way to make the two fields required upon check-in or somehow work this into TFS Check-In Policy?
Upvotes: 0
Views: 86
Reputation: 13116
You can write your own check-in policy:
or you can modify the state transitions in the work item template when the state changes.
http://msdn.microsoft.com/en-us/library/ms194981.aspx
If I had a way to go it would be the second way (and in fact I have done similar already at my work).