How to create a sprint in JIRA with some time already spent?

I've tried to create a sprint in JIRA with an issue that has some Time Spent already logged. I have set the start date of the sprint so that it should cover the period when that time was logged. However, no Time Spent is registered in the sprint. Does it mean it is impossible to create a sprint that has some time already logged at the beggining?

UPDATE: The main goal here is to have a burndown chart showing the actual history of the work logged also before creating the sprint.

Upvotes: 2

Views: 1131

Answers (1)

Nikhil Gupta
Nikhil Gupta

Reputation: 1778

This is not possible as of now. If you backdate your sprint in JIRA Agile, all the stories added would start appearing as added after the sprint start and thus candidates of scope change. We also face this situation often.