Is it ever possible to have two boundary event on a task?

A Boundary Event cancels the task it is on, is it ever possible to set two boundary events on a BPMN task?

I think not but the tool I'm currently using allows it.

I know None-Interrupting events can be multiple, but surely not Boundary Tasks...

Thanks

Upvotes: 0

Views: 1401

Answers (1)

Timotheus.Kampik
Timotheus.Kampik

Reputation: 2503

See the BPMN 2.0 specification, page 258 (288 in PDF document):

(One or more) Intermediate Events MAY be attached directly to the boundary of an Activity.

As the spec states one or more, it explicitly allows two boundary events to be attached to the same activity/task.

Upvotes: 1