Reputation: 3406
I have a TFS project setup with multiple teams. One of the team's backlog has disappeared even though it appears that everything is setup correctly. Let me detail it out:
I have the iterations setup for the team with the correct ones selected:
As you can see, the current sprint is Sprint 5. I have stories in this sprint as can be seen below:
But when I view my backlog, nothing shows. What else should I check?
Upvotes: 1
Views: 2377
Reputation: 114651
What is shown on the Sprint/Iteration Board is governed by 2 things:
If the template has been customized there is a third option, which not many people know about:
Upvotes: 4