I am using JIRA tool for project management activities and used to pull the data in excel on daily basis. The problem is when I am extracting the data, 'Time Spent' column data is coming in minutes and not in days. For the project tracking purpose I need data in number of days. I did some analysis to find out how I can change the option to pull the data in days but could not succeeded. It would be great if you can let me know the setting I need to enable/change to pull the data in desired format in excel. Thank you.
Upvotes: 1
Views: 1097
Reputation: 93
Using Script Runner plugin you can create a new scripted field with issue.timeSpent
(Long) divided correctly. In fact it holds seconds, not milliseconds, as documentation says. Then pull this field in Issue Navigator.