In JIRA Agile I know I can look at the sprint report to see all the issues completed in that sprint and manually count them.
I can also query for all issues completed in a particular sprint like:
project = MYPROJECT AND status = Done AND Sprint = nn
However what I want is a count of the total number of issues completed in each sprint. Is there a way to do this with JQL?
Upvotes: 3
Views: 9835
Reputation: 2564
I have set up a saved filter with:
project = MYPROJECT AND status = Done AND Sprint is not EMPTY AND issuetype in (Bug, Story)
Then on my dashboard I have added a Two Dimensional Filter Statistics gadget using:
This is actually better than just the total I wanted as I can also see the breakdown of bugs and stories in each sprint.
Upvotes: 5
Reputation: 26878
You can use the JQL query:
project = PRJKEY AND Sprint is not empty
and then use the pie chart (via Export > Chart > Pie Chart) to get the numbers:
Upvotes: 2
Reputation: 965
what about trying somehting like this:
project = MYPROJECT AND status = Done AND Sprint is not empty
i guess tha if the issue is added to a sprint you set this fiel up, if not it is empty. If true, this can help
Upvotes: 1