Where is timeline information stored in MS Project Server Database

Which table/view can I pull "Display on Timeline" checkbox info from the Project Server Database? I can see all Task Information from [MSP_EpmTask_UserView], [pub.Task]. The only data I can not find is "Display on Timeline". Anyone has experience with that?

screenshot

Upvotes: 0

Views: 446

Answers (2)

Yuran Liu
Yuran Liu

Reputation: 1

Found the timeline data in the table pub.MSP_PROJECT_FRONT_END

timeline data stored as XML format in PFE_PROPERTIES field

Upvotes: 0

Rod Gill
Rod Gill

Reputation: 31

Download the Project 2013 SDK from https://www.microsoft.com/en-us/download/details.aspx?id=30435

In it is the full schema for the Project Reporting database. Look especially at all the Views ending with _UserView as they have custom fields added automatically.

Upvotes: 1