I've managed to use the Job scheduling example for a project I'm working on. I have an additionnal constraint I would like to add. Some Resources should be blocked sometimes. For example a Global renewable Resource shouldn't be used between minutes 10 to 20. Is it currently already doable or if not, how can it be done in the score calculation ?
Thanks
Upvotes: 0
Views: 96
Reputation: 27312
Use a custom shadow variable listener to predict the starting time of each task.
Then simply have a hard constraint to check that the task won't overlap with its blocks. Penalize the amount of overlap to avoid a "score trap".