We have a small group < 4 but work on several different applications that we support. Each application gets its own Git repo, but as for managing the effort I really don't want to setup a separate team as well for each product.
Questions:
- For a small group working on several different products (eg. websites, services, utilities etc), can a single "team" within one project allow us to work on 2 sprints at the same time that are within different area paths?
- If I have already defined multiple teams, can I migrate all the content into the backlog of a single team?
- Assuming one team and multiple area paths, the project "hierarchy" would look something like this, correct?
Project
|__Team
Area-1
|__Sprint 1-n
Area-2
|__Sprint 1-n
Area-3
|__Sprint 1-n
[ update ]
On further inspection looking at the docs, the iterations can have their own paths.
It seems that if we want to manage 2 or more simultaneous sprints or overlapping sprints that involve different products, it makes sense to go ahead and configure a team per product or possibly one team per "business area" (eg. Sales, Operations, Warehouse etc). Within a business area, our group would only have 1 active sprint at a time, which seems straightforward, compared to trying to manage multiple sprints within the same team.
https://learn.microsoft.com/en-us/azure/devops/organizations/settings/set-iteration-paths-sprints?view=azure-devops
So the better approach might be multiple teams, with one (default) area per team and a iteration list for each team.
Upvotes: 1
Views: 3433
Reputation: 4035
The Team's areas and the Team's iterations are disjointed. I would think you could assign the different product areas (websites, services, utilities) to the team but then have just a single iteration list instead without trying to segregate the iterations by area. This won't work if the sprint dates for the different areas are different, but if they are different I don't think any approach you try to leverage in app will work.
Areas:
Sandbox
|__Team
|___Websites
|___Services
|___Utilities
Iterations:
Sandbox
|__Sprint 1
|__Sprint 2
|__Sprint 3
I don't think you will get to a good solution if the different product areas have different start/end dates for the sprint even if you could make something workable using the tool.
Upvotes: 2