What is the "Ideal Trend" line in TFS Sprint burndown chart based out of? Original Estimate or Remaining Work?
If I add more tasks mid sprint, my remaining work line will show a bump. Will the starting point of "Ideal trend" line also move up in this case?
Upvotes: 0
Views: 379
Reputation: 16163
You can find some explanation here: Sprint Burndown (Scrum).
The Ideal Trend line indicates an ideal situation in which the team burns down all of the effort that remains at a constant rate by the end of the sprint.
It is based on Remaining Work
and represent how you have to update your Remaining Work
in your sprint to get 0 hours of work at the end of a sprint. If you add new tasks after sprint start you will have non ideal line that adopted to new number of hours of tasks and duration of a sprint.