TFS 2018 Burndown chart

What is the "Ideal Trend" line in TFS Sprint burndown chart based out of? Original Estimate or Remaining Work?

If I add more tasks mid sprint, my remaining work line will show a bump. Will the starting point of "Ideal trend" line also move up in this case?

Upvotes: 0

Views: 379

Answers (1)

Shamrai Aleksander
Shamrai Aleksander

Reputation: 16163

You can find some explanation here: Sprint Burndown (Scrum).

The Ideal Trend line indicates an ideal situation in which the team burns down all of the effort that remains at a constant rate by the end of the sprint.

It is based on Remaining Work and represent how you have to update your Remaining Work in your sprint to get 0 hours of work at the end of a sprint. If you add new tasks after sprint start you will have non ideal line that adopted to new number of hours of tasks and duration of a sprint.