I have eleven sprint created,
but only 9 are showed at pending work.
How can I do to show future sprints, even all my sprints at pending work ?
Something I miss ?
Upvotes: 0
Views: 159
Reputation: 506
From the Work
tab, you need to click
To select iterations for the team, go to the default team's settings.
From here, click
You can then proceed to select the missing iterations from the list. They will then appear on your backlog list.
Upvotes: 1
Reputation: 5222
If you create a new sprint in project settings, you need to add the sprint to the team in your team settings to be able to see it in backlogs.
In settings, choose your team:
Or you can access it directly by adding the team name to the project settings URL:
Project settings url: .../{collection}/{project}/...
Team settings url: .../{collection}/{project}/{team}/...
Then you can check if "Iteration" contains all the sprints you need. If not, please click "Select iteration(s)" button and select the sprint you want to add.