Two persons with same roles (sysadmin) trying to change warehouse size ata same time? Which user instructions will execute first?
Upvotes: 0
Views: 48
Reputation: 26078
like every one else, there is no same time...
But also the warehouse resize is handled by the service layer, so there is an order there. I would assume the resize command for the second would be ignored, as it is "already in the process of a resize to the same size" if the sizes are different I would assume/hope the "last wins" but also could see the second getting an error with a resize is underway.
This is all based on the fact, that a resize leave the existing servers running while they complete, and starts queued/new queries on the new servers. Which firstly has to be spun up. So this is really a slow (in computer time) operation. And thus it's not a wild +1 type thing, as you explicitly set the size to something.