We have decided to go with a virtualization solution for a few of our development servers. I have an idea of what the hardware specs would be like if we bought separate physical servers, but I have no idea how to consolidate that information into the specification for a generalized virtual server.
I know intuitively that the specs are not additive - I shouldn't just add up all the RAM requirements from each machine to get the RAM required for the virtual server. I can't really treat them as parallel systems either because no matter how good the virtualization software is, it can't abstract away two servers trying to peg the CPU at the same time.
So my question is - is there a standard method to estimating the hardware requirements for a virtualized system given hardware requirement estimations for the underlying virtual machines? Is there a +C constant for VMWare/MS Virtual Server overhead (and if so, what is C?)?
P.S. I promise to move this over to serverfault once it goes into beta (Promise kept)
Upvotes: 5
Views: 14922
Reputation: 5343
Answers above are far too high, second (1 core per VM) is closer. You can either 1) plan ahead and probably over-purchase 2) add just-in-time. Do you have some reason that you must know well ahead (yearly budget? your chosen host platform doesn't cluster hosts, so you can't add later?)
Unless you have an incredible simple usage profile, it will be hard to predict before and you'll over purchase. The answer above (+25%) would be several times more than you need for an modern server virtualization software (VMware, Zen, etc) that manages resources smartly. It's accurate only for desktop products like VPC. I chose to rough it out on a napkin and profile my first environment (set of machines) on the host. I'm happy.
Examples of things that will confound your estimation
So, if you are using something like that doesn't do delta disks, disk space might be somewhat calculable. If lab manager (delta disk), disk space is really hard to predict.
Memory and processor usage: You'll have to profile or over-purchase heavily. I have many more guest CPUs than host CPUS, and don't have perf problems - but that's because of the choppy usage in our QA environments.
Upvotes: 2
Reputation: 7242
Yes add 25% additional resources to manage the VM. So if I need 4 servers that are equal to single core 2 ghz machines with 2 gigs of ram I will need 10 ghz processing power plus 10 gigs of ram. This will allow all systems to redline and still be ok.
In the real world this will never happen though, all your servers will not always be running all the time. You can get a feel for usage by profiling your current servers and determine their exact requirements and then adding an additional 25% in resources.
Check out this software for profiling utilization http://confluence.atlassian.com/display/JIRA/Profiling+Memory+and+CPU+usage+with+YourKit
Upvotes: 4
Reputation: 37668
The requirements are in fact additive. You should add up the memory requirements for each VM, and the disk requirements, and have at least one processor core per VM. Then add on whatever you need for the host system. VMs can share a CPU, to some extent, if you have really low performance requirements, but they cannot share disk space or memory.
Upvotes: 3