I would like to know if it is possible to pre-fix the value of some of the planning variables in the planning entity so that they cannot change during the optimization (i.e. fix that a specific job will be scheduled on a particular day).
Upvotes: 0
Views: 116
Reputation: 1029
It's possible to pin the entire planning entity so that OptaPlanner does not change the planning variable assignments there.
Please see the pinned Planning Entities documentation.